    SeaMade and DEME announce start offshore construction activities of the final and largest offshore wind farm ever built in the Belgian North Sea

    SeaMade and DEME announce that today the DP2 offshore installation vessel “Innovation” started with the first load out of the first 3 of the 58 wind turbine foundations and transition pieces for offshore installation, as support structure of the 8.4MW turbines. These foundations are the first to be hammered into the seabed for the SeaMade offshore wind farm.In addition, 2 foundations and transition pieces supporting the 2 substations will be installed in the coming months.

    The “Innovation” is sailing out of the “Maasvlakte 2” harbor area in the port of Rotterdam to the SeaMade concession areas for installation in the North Sea. The SeaMade project is the 8th and largest offshore wind turbine park in Belgium.

    The substation topsides and inter-array cables will be installed in spring of 2020 and the towers and nacelles will be mounted onto the foundations in the summer of 2020.

    SeaMade combines 2 offshore wind farms Seastar (252MW) and Mermaid (235MW) in the Belgian North Sea, 40-50 km from Ostend, encompassing 58 turbines of 8.4 MW. With a total aggregate capacity of 487 MW, it is the largest wind farm ever built in Belgium and the Belgian North Sea.

    From 2020, SeaMade will supply renewable energy for 500,000 households. A reduction of more than 600,000 tons of CO2 emissions is achieved with this.
     
    The monopile foundations range up to 80m with an average weight of nearly 1000t and an outer diameter of 8.0m. Connection to the transition pieces takes place via a pre-tensioned bolted flange connection. The steel foundations are protected against corrosion via a combination of ICCP (impressed current cathodic protection), coatings and corrosion allowance, subject to the different zones. Single layer scour protection has been installed at each individual monopile location. The 33 kV inter-array cable is designed and supplied by JDR and will connect each WTG to the relevant offshore substation in looped strings.

    In the concession zone of Mermaid and Seastar, 28 respectively 30 Siemens Gamesa wind turbines type SG-8.0-167 will be installed, with a Power Boost up to 8.4MW. The turbines are supported by a tower structure with a total length of approximately 90m and a bottom diameter of 6.0m, equally connected via a bolted flange connection to the transition piece.

    Both wind farms will be connected through two 220-245 kV XLPE 800mm² Aluminum submarine high voltage cables to the Belgian Modular Offshore Grid. The so-called export cables have a combined length of around 28km, and a cable diameter of around 247mm weighing approximately 96.4 kg per running meter and are designed and manufactured by Hellenic Cables. The installation activities will be done by DEME’s cable laying vessel Living Stone.

    Each of the Project’s two wind farms, Mermaid and Seastar, will have its own offshore substation, which will collect electricity produced, convert it from 33 kV to 220 kV and export it into the Offshore Grid operated by Elia System Operator NV, the Transmission System Operator. Capitalizing on a successful collaboration on numerous previous offshore wind farms, ENGIE Fabricom, Tractebel, Smulders and Geosea will be responsible for the full EPCI of the substations, including engineering, procurement, construction, transport, installation and commissioning.
     
    About DEME

    DEME is a world leader in the highly specialised fields of dredging, marine engineering and environmental remediation. The company can build on more than 140 years of know-how and experience and has fostered a pioneering approach throughout its history, being a front runner in innovation and new technologies.
    DEME’s vision is to work towards a sustainable future by offering solutions for global challenges: a rising sea level, a growing population, reduction of CO2 emissions, polluted rivers and soils and the scarcity of natural resources. Although DEME’s activities originated with the core dredging business, the portfolio diversified substantially over the decades, including dredging and land reclamation, solutions for the offshore energy market, infra marine solutions and environmental solutions
    While the company’s roots are in Belgium, DEME has built a strong presence in all of the world’s seas and continents, operating in more than 90 countries worldwide. DEME can rely on 5,200 highly skilled professionals across the globe. With a versatile and modern fleet of over 100 vessels, backed by a broad range of auxiliary equipment, the company can provide solutions for even the most complex projects.
    DEME achieved a turnover of 2.65 billion euros in 2018.
     
    About Otary RS NV

    The Otary partnership, is grouping various Belgian specialists in renewable energy: including investment and development companies Green Offshore and Power @ Sea, dredging and marine engineering specialist DEME and green energy players Aspiravi and Elicio. The Walloon environmental holding SRIW Environnement, and the Flemish and Walloon energy and utility holding companies Z-Kracht/Nuhma and Socofe are the Otary shareholders.
    In addition to the SeaMade concessions, Otary also holds the Rentel concession. The Otary partners shaped the offshore wind landscape in the Belgian Northsea. Otary partners are not only involved in SeaMade, but also C-Power, Northwind, Rentel and Norther, totalling 1.707 MW at sea, but also participate in other projects in Belgium and abroad.
     
    About ENGIE NV

    ENGIE Electrabel is part of the ENGIE Group, global leader in energy. ENGIE Electrabel is the largest energy supplier on the Belgian market, where it is active in electricity generation, sales of electricity and natural gas and energy services. The company offers value-added energy solutions as well as tailored services to its 2 million residential, professional and industrial customers. ENGIE Electrabel has a diversified production base of 9.529 MW in Belgium, close to its customers. It consists of facilities that operate from renewable sources, conventional and nuclear power plants. ENGIE Electrabel’s generation facilities are one of the lowest emitters of CO2 in Europe. The company is the country’s largest producer of green energy with a total capacity of 647 MW in renewable energy.
     
    About Eneco Wind Belgium NV

    With a production capacity of more than 1,000 MW, the Eneco group is a leading actor for the delivery and production of renewable energy and one of the largest players in the wind energy sector in the Benelux and the UK. Eneco Wind Belgium is the group company responsible for onshore and offshore wind energy generation in Belgium. Eneco Wind Belgium disposes of 96 onshore wind turbines (with a capacity of more than 200 MW) and has 25 % stake in the Belgian offshore wind farm Norther (44 turbines, 370 MW). Besides the production and distribution of sustainable energy, its main goal is to achieve global sustainability. The company with over 300 employees and business units in Mechelen, Gent and Waver, strives to deliver its 1 million customers with 100% sustainable and 100% locally produced energy by 2025.




27 ноября 2021

08:41 Грузооборот Бердянского морпорта (Украина) за 10 месяцев 2021 года снизился на 26,3%
08:22 Росморречфлот объявил конкурс реконструкцию ворот шлюзов Самарского гидроузла
08:16 Всемирный совет судоходства призвал ИМО предложить конкретные меры поддержки экологичного судоходства
08:00 ClassNK и морская администрация Панамы договорились совместно бороться с киберисками
07:45 ИАА «ПортНьюс» поздравляет с Днем рождения ректора ГУМРФ имени адмирала С.О. Макарова Сергея Барышникова!

26 ноября 2021

19:12 Состоялась встреча гендиректора «НТК» Михаила Кузнецова и губернатора Мурманской области Андрея Чибиса
19:00 Конкурс на реконструкцию базы техобслуживания флота Северного филиала Морспасслужбы приостановлен по жалобе
18:40 Буксир «Хохол» прибыл в порт Таганрог
18:18 В СПбГМТУ завершили очередные исследовательские испытания системы позиционирования и передачи данных
17:55 Прокуратура Кировской области добивается выплаты зарплаты работникам Сосновского судзавода
17:33 Крупнейший американский подрядчик GLDD получил контракт на дноуглубление судоходного канала в Хьюстоне
17:14 ОСК открыла «Фабрику процессов» в Калининграде
16:58 IMO назначила специального советника по безопасности на море
16:37 Сухогруз «Спарта» доставил из Сирии партию фруктов
16:16 Вышел итоговый номер журнала «ПортНьюс» за 2021 год
15:58 «Новороссийское морское пароходство» выставило на торги акции за 4,6 млн руб.
15:46 В Мурманской области инвестиции в реализацию проектов для обеспечения эффективного использования СМП составлают 112,9 млрд руб.
15:21 Паромная переправа Ванино-Холмск закрыта до улучшения погодных условий
14:54 Невский ССЗ заложил два научно-исследовательских судна проекта 17050
14:36 Навигацию в Азово-Донском бассейне продлят до начала декабря
14:14 Правительство РФ утвердило Транспортную стратегию до 2030 года с прогнозом до 2035 года
13:50 «Атоммаш» приступил к отгрузке ёмкостей СПЗАЗ для энергоблока №1 АЭС «Аккую»
13:31 Начальник плавдока «82-го Судоремонтного завода» пойдет под суд за нарушения правил безопасности при доковании «Адмирала Кузнецов»
13:07 СНСЗ спустил на воду корабль ПМО проекта 12700 «Анатолий Шлемов»
12:48 Хабаровский судзавод получил свидетельство о признании РРР
12:29 Чистая прибыль ПАО «ТрансКонтейнер» по МСФО за 9 месяцев 2021 года выросла на 51,2%
12:10 Ледокол «Новороссийск» провел сухогруз «Радик Баширов» из Певека до чистой воды
11:54 Завод «Красное Сормово» начал новый этап программы производительности труда
11:34 Пассажиропоток на речных маршрутах в Московской области вырос в навигацию-2021 на 30%
11:17 Судзавод «Вымпел» намерен расширять поставки в страны АТР
10:55 Мировой бункерный рынок завершает рабочую неделю умеренными разнонаправленными колебаниями - аналитики MABUX
10:33 В ЯНАО суд обязал поднять и утилизировать останки судов, затонувших в акватории реки Обь
10:12 В порту Кавказ предлагают оставить рейдовую перевалку
09:51 Председателем совета директоров ОАО «Владморрыбпорт» избран Валерий Мартынов
09:30 Индекс стоимости фрахта Baltic Dry 25 ноября
09:09 Глава Минвостокразвития предложил ввести единое управление Северным морским путем
08:48 Нефть дешевеет на опасениях по сокращению спроса
08:29 Начинается второй этап строительства Багаевского гидроузла
08:00 Ледокол «Диксон» провел застрявшее во льдах судно «Георгий Ушаков» в бухту Север

25 ноября 2021

19:00 Система сокращения выбросов Damen получила сертификат соответствия стандартам Евросоюза (ЕU Stage V)
18:40 Росморпорт проведет аукцион на проект создания в Большом порту Санкт-Петербург искусственного земельного участка и объектов Базы СНО на нем
18:18 «Роснефть» начинает строительство нефтетранспортной системы «Восток Ойл»
17:46 «Адмиралтейские верфи» планируют осуществить ремонтное дноуглубление на участке р. Нева
17:19 ГК «Дело» представила стратегию цифровизации
16:43 В Азербайджане обсудили навигационную безопасность на Каспии
16:16 Аварийно-спасательное судно «Спасатель Заборщиков» вывело из Анадырского лимана сухогруз «Геннадий Цыганков»
15:58 ПНТ ожидает объем перевалки нефтепродуктов по итогам 2021 года на уровне прошлого года
15:35 На Чукотке завершена топливная навигация
15:18 Грузооборот Азово-Донского бассейна в 2021 году сократился на 14%
14:54 Госдума ратифицировала Найробийскую конвенцию об удалении затонувших судов 2007 года
14:34 Mitsubishi Heavy Industries поставит оборудование для завода по производству СПГ в Усть-Луге
14:15 В СовФеде предлагают установить нулевую ставку НДС на судоремонт
13:56 «Ростерминалуголь» за 10 месяцев 2021 года отгрузил на экспорт 21 млн тонн угля
13:33 «Черномортранснефть» провела биомониторинг водной среды акватории Черного моря
13:17 Росатомфлот представил проекты, реализованные в рамках международной технической помощи
12:52 Ледокольные проводки в порту Архангельск начнутся с 26 ноября
12:31 Проект запуска прогулочных электросудов по Енисею из Красноярска оценивается в 1,3 млрд руб.
12:13 Администрация Обского бассейна и судовладельцы определили план совместной работы по улучшению безопасности судоходства
11:53 Профицит российских портовых мощностей и дефицит провозной способности ж/д сдерживают грузооборот со странами АТР - эксперт
11:32 «Эльгауголь» приостановил вывоз угля с Огоджинского месторождения