• 2018 August 7 14:13

    Port of Long Beach Middle Harbor Terminal redevelopment project Phase 3 is on track

    The third and final phase of the Middle Harbor Terminal Redevelopment Project is underway and on track to be completed on time and on budget. When finished, the facility operated by Long Beach Container Terminal (LBCT) will be a 311-acre modern marvel equipped with the most advanced technologies in North America and the cleanest available cargo handling equipment, the port authority press release said.

    “Phase 3 completes the creation of the most innovative, efficient and clean terminal in the Americas,” said LBCT President Anthony Otto, who has worked with the Port on the modernization project from concept to fruition. “We’ve had tremendous success with the first two phases, and we’re excited to be closing in on full build-out.”

    Construction began in 2011 on the container terminal designed to handle more than twice as much cargo as the two older terminals it is replacing. At completion, the facility will have an annual capacity of 3.3 million TEUs (twenty-foot equivalent units). Key features include a 4,250-foot-long concrete wharf for working three big ships simultaneously, 14 dual-hoist super post-Panamax cranes to accommodate 22,000-TEU ships, and an on-dock rail yard for moving 1.1 million TEUs a year.

    LBCT’s state-of-the-art cargo handling equipment runs on electricity or alternative fuels. Electric-powered cranes and container transport vehicles move containers to and from ships at berth and within the container and rail yards. Alternative fuel vehicles move containers from the container yard to the rail yard.

    To date, LBCT has invested more than $650 million in technology and equipment.
    When finished, the terminal will employ 70 automated stacking cranes, 72 guided container transport vehicles, 50 terminal yard tractors, five dual cantilever gantry cranes within the rail yard, and multiple dedicated reefer stacking structures with a total capacity for 2,250 refrigerated cargo containers.
     
    The Port’s construction budget for Middle Harbor is $1.493 billion. The first two phases totaled about $1 billion, and the cost of the final phase is estimated at $470 million.

    “Middle Harbor is a feat of engineering and a model of sustainability,” said Port Executive Director Mario Cordero. “Once the final phase is built and operating at full capacity, the Middle Harbor Terminal alone would rank as the nation’s sixth-busiest container port.”

    Phase 3
    The project’s final phase centers on the last 112 acres: building out the container yard, extending the wharf to its full length of 4,250 feet and completing the on-dock rail yard. Highlights include:

    • Constructing a retention dike to complete the last stage of fill
    • Driving more than 475 concrete piles to support the last 1,470 feet of wharf
    • Adding 11 container storage blocks to the terminal’s container yard for a total of 36 dedicated areas for stacking containers
    • Laying an additional 54,000 linear feet of track to complete the terminal’s 73,000-foot network of on-dock rail track
    • Building a south truck gate complex, the second of two truck gates servicing the entire terminal
    • Constructing the nearly 21,000-square-foot administration building and related parking and solar carports

    Phase 3 work on the wharf and backlands began in February, the on-dock rail yard expansion started in March, and recent milestones include the arrival of new ship-to-shore cranes 11 and 12 in early June. The Port expects to begin the bidding process for the contract to build the administration offices in September. The latter will be the facility’s fifth green structure built to Leadership in Energy and Environmental Design (LEED) sustainability standards.

    Like the first two phases, Phase 3 components are designed to maximize energy efficiency, resource conservation and recycling of materials from demolished structures. Environmental highlights of the final phase include:

    • Reusing approximately 1.4 million cubic yards of dredge sediments as fill to support the construction of the last segments of wharf and container yard
    • Recycling demolished concrete and asphalt from the previous structures and paved areas to use as crushed miscellaneous base material for the foundation of the new yard pavement

    “Every aspect of this project is an example of the Port’s environmental stewardship,” said Senior Program Manager Monique Aguilar, who oversees day-to-day operations of the terminal redevelopment project.

    As part of Phase 1, the Port built a battery-exchange building for charging, storing and exchanging batteries to support the zero-emissions container transport vehicles at the terminal. During Phase 3, the Port will construct a second battery-exchange building as a backup support facility to ensure resiliency and reliability of terminal operations.

    Corporate changes
    The project has not been affected by corporate changes to LBCT’s parent company, Hong Kong-based Orient Overseas International Ltd. (OOIL), which is being acquired by China’s state-owned COSCO Shipping. In response to national security concerns raised by U.S. regulators, COSCO agreed to sell LBCT to complete the $6.3 billion takeover of OOIL.

    While the sale of LBCT is pending, ownership of the terminal operator is expected to be transferred to a trust. The new owner would take over the historic 40-year, $4.6 billion lease with the Port that OOIL signed in 2012.

    The COSCO-OOIL merger is the latest in a series of consolidations that have swept through the maritime industry in recent years. As a result, COSCO, the ocean carrier with the world’s fourth-largest container fleet, and OOIL, which has the eighth-largest shipping fleet, will emerge as the world’s third-largest ocean shipping company.

    “None of this activity has slowed the flow of cargo or the construction schedule on the ground,” Otto said.

    Completing Middle Harbor
    The first phase, which opened in 2016, and the second phase, which opened in 2017, completed 197 acres of new terminal, including two berths for the next generation of megaships calling now or in the future at the Port. Completing the Gerald Desmond Bridge Replacement Project will free up 2 more acres to finish the north truck gate complex, bringing the total terminal area to 311 acres when the third and final phase is done.

    As it did in the earlier phases, LBCT will begin testing new equipment as each segment of Phase 3 is built. Construction is due to be completed by December 2020, with the last phase commissioned in March 2021.

    As the Port completes the Middle Harbor Terminal Redevelopment Project, it will embark on its next major capital project, the Pier B On-Dock Rail Support Facility. The large-scale support facility, along with smaller rail improvement projects, represents an investment of nearly $1 billion to expand rail capacity, increase operational efficiency and further reduce emissions throughout the Port by moving 35 percent or more of container cargo by rail instead of by truck. Considered the linchpin of the Port’s rail network, the Pier B On-Dock Rail Support Facility would be a modern, full-service staging area for storing, sorting and assembling 10,000-foot trains.

    The new Pier B rail yard will also be built in phases and construction is expected to take about a decade. Currently, the Port is evaluating which segments to build first so terminal operators can get the highest use of their on-dock rail yards as soon as possible, said Sean Gamette, the Port’s Managing Director of Engineering Services.

    “We’re looking at what early actions would enhance cargo operations for our tenants, their customers and the entire supply chain,” Gamette said.




16 июля 2024

17:36 Южнокорейская STX Heavy Industries изменит название на HD Hyundai Marine Engine
17:14 Ряд морских контейнерных перевозчиков впервые за долгое время стал снижать спотовые ставки
16:47 Земснаряд «Кадош» Росморпорта отправится в доковый ремонт
16:25 В Сербии планируется реконструкция дунайского порта Прахово за счет госбюджета
16:04 Пакет акций «Логин Дело» Сергея Шишкарева в АО «Корсаковский морской торговый порт» составил 64,26%
15:46 В бункерном топливе региона Амстердам-Роттердам-Антверпен обнаружено высокое содержание абразивных частиц
15:28 Губернатор: Площадку для белорусского порта в Приморье выберут в 2024 году
15:11 Череповецкий судозавод передал ГТЛК третью баржу проекта RBD4608
14:57 Трехпалубный теплоход «Сергей Есенин» выполнил первую швартовку к новому причалу в Великом Новгороде
14:39 РКО начало техническое наблюдение за строительством третьего земснаряда проекта 93.159А
14:02 Китайская Yangzijiang Shipbuilding планирует расширить свои судостроительные мощности
13:38 Генеральным директором завода «Красное Сормово» назначен Станислав Кругляшов
13:20 Новороссийский зерновой терминал в сезон 2023/2024 отгрузил 168 судов
13:01 СНСЗ заложил тринадцатый морской тральщик проекта 12700 «Виктор Корнер»
12:39 Премьер-министр Дагестана: Товарооборот с Ираном пока реализован на 10-15%
12:21 Завершено совместное российско-китайское морское патрулирование в Южно-Китайском море
12:02 Первый в России водородный полигон запущен в Южно-Сахалинске
11:46 В Ростове-на-Дону спущен на воду плавучий причал для швартовки пассажирских судов
11:17 Танкеры ASCO в январе-июне 2024 года снизили грузоперевозки на 20% — до 2 млн тонн
10:56 Спуск к причалу и зал ожидания для пассажиров теплоходов обустроят в Хопылеве (Ярославская область)
10:35 Контейнерные перевозки на СКЖД в январе-июне 2024 года снизились на 7,6% — до 91,5 тыс. TEU
10:17 РС актуализировал Правила постройки танкеров для перевозки сжиженных газов
09:58 В Приморье заказчику передан первый композитный катамаран класса «Тихоокеанский 108»
09:44 В Пермском крае выставили на продажу причал Чайковского речного порта
09:32 Росморречфлот предлагает активнее использовать транзитный потенциал речных артерий Приморья
09:09 Баржа получила повреждение корпуса при прохождении порога на Енисее
08:46 Состояние гидротехнических сооружений ВМТП проинспектировано руководителями отраслевых ведомств
08:23 Анадырский морской порт (Чукотка) с начала навигации обработал около 30 тыс. тонн угля
08:00 Обновлены сведения о фактических глубинах и проходных осадках судов на акватории порта Посьет (Приморье)

15 июля 2024

19:00 Подготовка к Главному Военно-Морскому параду внесет изменения в график разводки мостов в Петербурге
18:35 Администрации «Волго-Балт» передан земснаряд проекта Ц480Д «Константин Безюков»
18:13 Мнение: Развитие арктических проектов требует инновационных подходов для подготовки кадров
17:54 Инвесторы могут продлить сроки строительства судов по первым крабовым аукционам до 7 лет
17:36 В Рыбинске началась погрузка секций плавдока для ПСЗ «Янтарь»
17:19 Турция сократит импорт пшеницы в сезоне 2024/2025 на 16% — до 8 млн тонн
16:58 На площадке «Красные Баррикады» ЮЦСС капитально отремонтируют плавучую буровую установку «Бриз» «Лукойла»
16:37 Датская Torm купит на вторичном рынке восемь танкеров-продуктовозов и продаст один типа MR
16:15 Продажи бункерного топлива в порту Сингапур за январь-июнь 2024 года выросли на 8,5%
15:54 Основной акционер Судоремонтно-судостроительной корпорации (Нижегородская область) снизил свою долю до 27,8%
15:36 Грузооборот порта Сингапур за январь-июнь 2024 года увеличился на 8,2%
15:21 Соглашение Maersk и Hapag-Lloyd о совместном флоте на контейнерных линиях вызвало вопросы у властей США
14:48 Сделка о покупке STX Heavy Industries компанией HD KSOE одобрена антимонопольными органами Южной Кореи
14:23 На Байкале пресечены нелегальные пассажироперевозки на судах в районе поселка Листвянка
13:59 Реконструкция порта Корсаков (Сахалин) будет выполнена в 2024-2027 годах
13:47 Совокупный контейнерооборот терминалов COSCO за первое полугодие 2024 года вырос почти на 8%
13:05 НЭС «Михаил Сомов» доставило снабжение на остров Визе
12:32 Совокупный грузооборот терминала CSP Abu Dhabi с момента запуска превысил 5 млн TEU
12:04 Российско-китайское учение «Морское взаимодействие – 2024» пройдет с 15 по 17 июля
11:44 Заместителем генерального директора РС назначен Алексей Березин
11:36 Таможня в порту Ростов-на-Дону в первом полугодии 2024 года оформила более 2 тыс. судов
11:27 РС: Автоматическая система обмена данными в диапазоне очень высоких частот сменит существующую АИС
11:11 Судопогрузочные машины доставят на терминал минудобрений в Усть-Луге в сентябре 2024 года
10:48 В порту Находка (Приморье) планируется реконструкция причала №25
10:29 «НОВАТЭК» в первом полугодии 2024 года снизил реализацию природного газа на 3,3%
10:12 Петербургский суд постановил взыскать с Wartsila 7,6 млн евро в пользу Балтзавода
09:53 Ученые саратовского вуза запатентовали модель гребного винта для арктических судов
09:31 Атомоход «Сибирь» завершил ледокольную проводку двух судов в порт Певек
09:08 Пассажиры речных электросудов в Москве с момента запуска регулярных маршрутов совершили 1 млн поездок
08:45 Навигация 2024 года открылась в порту Тикси (Якутия)
08:22 Часть акватории Татарского пролива предоставлена в обособленное водопользование погрануправлению ФСБ
08:00 Готовится к публикации третий номер журнала «ПортНьюс» за 2024 год

14 июля 2024

11:11 Грузооборот турецких портов в январе-июне 2024 года вырос на 3,2% — до 269,1 млн тонн
09:29 На реке Индигирка в Якутии столкнулись два теплохода
08:40 Перевалка зерна на терминалах «Деметра-Холдинг» по итогам сезона составила 12,5 млн тонн
08:23 Председателю совета директоров Московского речного пароходства Вадиму Березину 88 лет!

13 июля 2024

15:21 Китай успешно применяет «морскую милицию» для контроля над спорными водами без вооруженного конфликта
13:51 Правительство РФ снизило порог обязательной репатриации валютной выручки
13:42 Михаил Мишустин утвердил распределение обязанностей кураторов ряда федеральных и национальных проектов
12:38 Петербургский городской причал у Летнего сада оборудуют новым металлическим понтоном

12 июля 2024

19:00 Учебный парусник «Мир» Росморпорта принял вторую в 2024 году смену практикантов